Computer Certification

  1. Home
  2. Computing & Technology
  3. Computer Certification

PMP Practice Test Answers

Answers 1-5

by Dori Reuscher
for About.com

All material written and provided by Whizlabs.

Next 5 Questions

Answer 1

Correct Choice:
B

Explanation:
The ‘Delphi technique’ is a commonly used tool to secure expert judgment while initiating a project.

‘Peer review’ is a project selection tool, ‘Expected value’ is a method quantitative risk analysis, and ‘WBS’ is a project planning tool.

Answer 2

Correct Choice:
B

Explanation:
Project III has an IRR of 15%, which means the revenues from the project equal the cost expended at an interest rate of 15%. This is a definitive and a favorable parameter, and hence can be recommended for selection.

Project I has an unfavorable BCR and hence cannot be recommended.

Information provided on projects II and IV is not definitive, and hence neither of projects II and IV qualifies for a positive recommendation.

Answer 3

Correct Choice:
C

Explanation:
A WBS is a deliverable oriented grouping of project components that organizes and defines the total scope of the project.

Answer 4

Correct Choice:
D

Explanation:
A start-to-finish (SF) relationship between two activities implies that the completion of successor is dependent on the initiation of its predecessor.

A finish-to-start (FS) relationship between two activities implies that the initiation of successor is dependent on the completion of predecessor.

A finish-to-finish (FF) relationship between two activities implies that the completion of successor is dependent on the completion of predecessor.

A start-to-start (SS) relationship implies that the initiation of successor is dependent on the initiation of predecessor.

Answer 5

Correct Choice:
B

Explanation:
The project team must complete a scope statement for developing a common understanding of the project scope among stakeholders. This lists project deliverables – summary level sub-products, whose full and satisfactory delivery marks the completion of the project.

Scope verification is the process of securing a formal acceptance of the project scope by stakeholders.

Scope definition is the process of subdividing the major project deliverables into smaller, more manageable components.

A risk management plan involves setting up processes for identifying and dealing with project risks.

Next 5 Questions

Explore Computer Certification

About.com Special Features

Computer Certification

  1. Home
  2. Computing & Technology
  3. Computer Certification
  4. Certifications by Job Role
  5. Project Management
  6. PMP Practice Test Answers

©2009 About.com, a part of The New York Times Company.

All rights reserved.