Answer 11
Correct Choice:
A
Explanation:
In a functional organization, the project team members have dual reporting to two bosses the project manager and the functional manager.
In a weak matrix organization, the power rests with the functional manager.
In a balanced matrix organization, the power is shared between the functional manager and the project manager. A projectized organization is grouped by projects and the project manager has complete control on the project and its team.
A Tight matrix organization refers to co-locating the project team and has nothing to do with a matrix organization.
Therefore, a project manager would find it difficult to drive team development in a weak matrix organization.
Answer 12
Correct Choice:
A
Explanation:
Number of communication channels with n members = n*(n-1)/2
Originally the project has 25 members (including the project manager), which makes the total communication channels as 25*24/2 = 300.
With the addition of the quality professional as a member of the project team, the communication channels increase to 26*25/2 = 325.
Therefore, the additional channels as a result of the change, that is, 325-300 = 25.
Answer 13
Correct Choice:
A
Explanation:
Project records should be prepared for archiving by the appropriate parties.
Answer 14
Correct Choice:
B
Explanation:
Common formats for Performance Reports are, bar charts (also called Gantt Charts), S-curves, histograms and tables etc.
Answer 15
Correct Choice:
C
Explanation:
Choice C is the correct answer.
Positive Schedule Variance means the project is ahead of schedule; Negative Cost Variance means the project is over-budget.